Site: Wapping Wharf
Dates: June 14 – December 15
Size of project: 194 Apartment within 2 x 5-6 storey blocks
Type of work that was commissioned:
The Wapping Wharf project was run on a design build basis and consisted of a communal heating scheme where we installed 2 x 533Kw Hovel twin boilers and 2 x 20kw CHP boilers which fed each apartment which in turn were then fitted with an evinox heat exchange unit which fed a wet central heating system with radiators.
A full mechanical installation was also carried out involving apartment fit outs including all bathrooms and water supplies, boosted cold water, dry risers, rainwaters and soils and all apartment ventilation and ducting.
A 65 panel, 16.75Kw solar PV system has also been installed on an a-frame installation to the flat roof of the development.
Case Study: Paint Works, Bristol
10 March 2018
£6200 Raised for Cystic Fibrosis Trust
23 June 2017
Malmesbury Nursing Home
26 May 2017
St Michaels Court –Wilmot Dixon / PfP
4 May 2017
Orchard House, Shirehampton – Places for People Sheltered Housing Scheme
4 May 2017
Westbury on Trym Methodist Church, Bristol – H Sweet & Sons
1 February 2017
Follow us
`